South Park Improvements

Master Plan and Improvement Project

The South Park improvement project includes: renovation of the playground, addition of a picnic shelter with restrooms, resurfacing of three tennis courts and addition of four pickleball courts, addition of a walking path, renovation of the existing shelter, and addition of a rain garden.

View Master Plan

South Park Improvements

Overview

March 2023 - We are excited to share that the Park Ridge Park District was a recipient of an Open Space Land Acquisition and Development (OSLAD) grant in the amount of $600,000 to be used for improvements at South Park. The Park Ridge Park District’s South Park project is one of 118 local recreation projects representing $60 million in funding assistance approved for 2023 OSLAD grant funds. The $600,000 grant received is the maximum amount awarded by OSLAD for development projects, and requires the Park District to match the grant amount received. The District will provide the required matching funds from our Capital Projects Fund.

Planning Process

A community input meeting was held on Tuesday, November 7, 2023 to gather feedback on the proposed options for the new playground. A video of the meeting and copy of the presentation is available for those who were unable to attend. 

View Presentation View Recording

The Park District also held a community planning meetings in the Fall of 2022 to determine what will be included in the master plan and the grant submission. Links to the Fall 2022 planning meetings are located below. The South Park master plan includes: renovation of the playground, additional of a picnic shelter with restrooms, resurfacing of three tennis courts and addition of two pickleball courts, addition of a walking path, renovation of the existing shelter, and addition of a rain garden.

View Presentation View Recording

Timeline

  • Design Development and Construction Documents: through December 2023

  • Bidding: February 2024

  • Permitting: Spring 2024 - Summer 2024

  • Construction: Autumn 2024 - Spring 2025

Updates

November 20, 2024 - The poured in place surfacing has been installed at the playground, and the engineered wood fiber will be installed around the swings and the playground soon. The playground will be opened once concrete work has been completed.

Concrete installation around the shelter and connecting pathways is underway. Construction continues on the restroom facility/picnic shelter. The tennis/pickleball courts have been paved, and net post footings were poured. The color coating and lining will occur as soon as weather allows in 2025, which most likely will be around Memorial Day.

October 17, 2024 - The playground equipment installation is nearing completion. The contractor is targeting for the playground surface to be installed this fall, weather permitting. The restroom/picnic pavilion infrastructure is installed. The asphalt for the tennis/pickleball courts is being poured this week. 

Additional sewer issues, including 50 feet of collapsed pipe, have been discovered on the project. An updated plan has been submitted to MWRD. Stormwater and sanitary sewer work cannot be completed until this is approved. 

September 19, 2024 - Concrete curb for the playground and concrete footings for the tennis court fencing was installed this week. The tennis court fencing will be installed next week. The playground is scheduled to be delivered the first week of October.

September 12, 2024 -  Tennis court fencing will start this week. Curbing for the tennis courts will be poured next week, weather permitting.

August 21, 2024 -  Construction has begun at South Park starting with the tennis courts and playground. 

August 12, 2024 - Last week, the full permit for the project was issued  by the City. Private utility locate occurred on Monday. The construction fence and demolition will begin this week starting with the tennis courts and playground. 

June 28, 2024 - MWRD has sent our permit up for final review. This process can take a week or two, but we expect the permit to be issued soon. 

June 7, 2024 - MWRD has replied with new and different comments for the engineer, and we are working to address the comments for resubmittal.

May 3, 2024 - A preconstruction meeting took place this week. We are still waiting for permit approval from Metropolitan Water Reclamation District (MWRD). The project will begin once the permit is issued.

April 19, 2024 - A preconstruction meeting is to be scheduled at the end of the month.

February 21, 2024 - The project went out to bid on February 15, and a pre-bid meeting was held on-site on February 20. Bids will be opened on March 5.

February 1, 2024 - The project is scheduled to go out to bid on February 15.

December 21,2023 - The plans have been submitted for permitting.

December 6, 2023 - Plans are 90% complete and will be submitted this month for permitting. The project will go out to bid in February 2024.

November 8, 2023 - A virtual community meeting was held on November 7 for input on the playground design. Please see the Planning Process section above for a recording of the meeting and a copy of the presentation.

October 19, 2023 - Staff met again with Upland Design for a design development meeting for the playground. Upland Design has developed three playground plans for public input which will be presented a the public input meeting schedule for November 7. The results of the meeting will help shape the direction of the playground. More information about this meeting is located further up on this page under the Planning Process section. 

September 27, 2023 - Staff met with Upland Design to review playground options for the project. A community input meeting will be scheduled to gather public input on the project. Please check back for more information on that meeting. 

September 7, 2023 - Staff is working with Upland Design, the architects on this project, on design options for the playground. A community input meeting will be held this Autumn to gather feedback and better understand the community's needs regarding the playground. Please check back for more information.